Sharjah, Waste to Energy Facility (DUBAI, U.A.E.)
Sharjah Waste to Energy Unit
02

May 2020

Posted by Equilibre

Our mission for this project is approaching its completion. The facility will have an annual treatment capacity of 300,000 tons of waste, or 37.5 tons per hour, and will produce a net energy output of 29 MW.

We were committed alongside SETEC Energie-Environnement by having a varied set of substations at our charge:

  • Contribution (steel structure part) to the technical specifications of the execution design project;
  • Assistance to our client for the design and dimensioning of the steel structure of the Waste Bunker building. Execution study of the assemblies and runway girders of the overhead crane (double crane, capacity 22 tons);
  • Execution design study of the structure, the assemblies, the overhead crane runway girders (60 t) and the secondary structures of the Turbine Hall building;
  • Execution design study of the structure, composite floors and assemblies of the Workshop building;
  • Execution design study of the structure and assemblies of the Good’s Lift (attached to the Boiler building).

Client: SETEC Energy-Environment

Manufacturer: CNIM

Client : Masdar and Bee’ah

Other News

Share This